Purchasing and planning

Europe/Berlin
Description

Kapton purchase

  • Splitting has been submitting the CERN purchasing, waiting for feedback
  • Testing:
    •   Irradiation is complete, documenting the inspection results this morning
    •  Pull test will need one the order a week.
    •  No way of performing bonding test unfortunately
  • Material specification will be arriving soon, ask Bernd for comments

3M Tape

  • Waiting for 3rd company for a quote
    • Bernd has requested this, should be here this week (hopefully early this week)

CuW Metal

  • Initial agreement was that we disregard flatness for the full sheet now.
  • Apparently the plates are too thin?
    • Request that we received the plates regardless? Requesting for more details on how widespread this thickness issue is.
    • Supposedly there are 83 KIT variants are ready. Request to have this be send to KIT as soon as possible
      • Suboptimal cutting path is fine, get the LD Fives to be produced ASAP

 

There are minutes attached to this event. Show them.
    • 1
      General discussions
      Speakers: Erik Butz, Maria Toms, Markus Klute, Yi-Mu Chen