Kapton purchase
- Splitting has been submitting the CERN purchasing, waiting for feedback
- Testing:
- Irradiation is complete, documenting the inspection results this morning
- Pull test will need one the order a week.
- No way of performing bonding test unfortunately
- Material specification will be arriving soon, ask Bernd for comments
3M Tape
- Waiting for 3rd company for a quote
- Bernd has requested this, should be here this week (hopefully early this week)
CuW Metal
- Initial agreement was that we disregard flatness for the full sheet now.
- Apparently the plates are too thin?
- Request that we received the plates regardless? Requesting for more details on how widespread this thickness issue is.
- Supposedly there are 83 KIT variants are ready. Request to have this be send to KIT as soon as possible
- Suboptimal cutting path is fine, get the LD Fives to be produced ASAP